North K Street Reconstruction
This project will reconstruct the pavement structural section of North K Street from Elm Street to Chestnut Street and Elm Street from North L Street to North K Street and move curb and gutter to accommodate bioswales required by new Regional Water Quality Control Board C.3.9 treatment requirements for reconstruction projects that result in replacement of at least 1 acre. The new curb layout will lower vehicular traffic speeds by reducing lane width and introducing curb return bulb outs at intersections improving pedestrian safety. This street selected for reconstruction has a PCI under 25 and is consistent with the City’s 2024 Pavement Management Budget Options Report prepared utilizing the MTC StreetSaver database and City’s Pavement Management Program tools.
The preliminary design documents for this project may be viewed under additional resources below in preparation for the meeting.